MIC-003 — Ravensfield Junction Upgrade | Reporting Period: April 2026 | Last updated: 08 May 2026 14:32

Estimated Final Value
£67,300,000
+£180,000 vs prev
Estimated Final Cost
£61,180,000
+£120,000 vs prev
Net Margin %
9.10%
+0.12% vs prev
Period Turnover
£2,300,000
In period

Cumulative Position

MetricEstimated Final Value (£)Estimated Final Cost (£)Margin
Original Contract38,400,00036,120,0005.94%
Estimated Final42,500,00039,550,0006.94%
Cumulative to Date28,310,00026,420,0006.68%
Previous Period27,070,00025,230,0006.79%
Period Movement1,240,0001,190,000+0.12%

Health Indicators

  • Cost Ledger Matched to Accounting System
  • Change Register Current (47 events)
  • Risk Register Updated
  • Programme Not Uploaded
  • 3 Changes Disputed (£210,000)
  • CVR Summary Reconciled

Cumulative Value vs Cost — Project Lifecycle