Estimate & Award
Contract baseline, team and indexed documents
Contract Details
Contract TitleRavensfield Junction Upgrade
Project ReferenceMIC-003
Client / EmployerParagon Infrastructure JV
Form of ContractFIDIC Yellow
Financial
Original Contract Sum£61,000,000
Current Estimated Final Value (incl. changes)£67,300,000
Change since award+£4,100,000 (+10.7%)
Programme
Start Date20 Aug 2024
Planned Completion15 Apr 2028
Forecast Completion10 Apr 2028 (14 days early)
Duration130 weeks
EOT Awarded / Applied / Outstanding0 / 0 / 0 weeks
Liquidated / Delay Damages£0
Project Team
Contracts DirectorP. Lindholm
Project ManagerA. Kowalski
Quantity SurveyorT. Bevan
MiQSBot has indexed all uploaded contract documents and knows this is a FIDIC Yellow project. All contractual advice is grounded in the correct terminology and clause references for this contract form.
Primary Contract
Northgate Viaduct — Executed Contract.pdf
✓ AI Indexed
MiQSBot has read this document.
Contract Documents
- Particular Conditions✓ Indexed
- Employer's Requirements✓ Indexed
- Contractor's Offer✓ Indexed
- Schedules✓ Indexed