MiQSMIC-002
JH

Cost Plan — April 2026

Last updated: 08 May 2026 14:32 by L. Pemberton

High-Level Summary

SummaryBudget (£)Estimated Final Cost (£)Cost to Date (£)Period (£)Variance (£)
People (Staff + Labour + Prelims)14,200,00012,840,00010,920,000480,000+1,360,000
Plant & Equipment9,800,0009,210,0007,640,000310,000+590,000
Materials8,400,0007,980,0006,420,000195,000+420,000
Subcontractors6,000,0005,720,0004,890,00088,000+280,000
Overhead (8%)2,966,2502,490,000117,000
TOTAL Estimated Final Cost38,400,00037,750,00032,360,0001,190,000+650,000

Ask MiQSBot to explain any cost movement — e.g. 'Why has Labour increased this month?' or 'Break down the Plant overspend'.

Period Cost Movement Explanations

Log the reasons for cost changes this period for Pre-CVR review

#DescriptionCategory£ Value
1
2
3
4
5