Risk & Opportunity

Risk Provision register

Total Risk Provision
£820,000
Traded in CVR
£740,000
Net Exposure
£80,000
Opportunity Pool
£95,000
#DescriptionTypeRisk Cost (£)Period ΔOwnerResolutionComments
1Ground condition variance — Section 4B underpinningRisk£240,00012,000 L. PembertonInvestigation in progressAwaiting GI report
2Design development risk — deck connection detailRisk£185,000£0S. OkaforOpen
3Third party delay risk — Network Rail possessionsRisk£160,000£0S. OkaforOpen
4Material price escalation — structural steelRisk£95,0008,000 L. PembertonReducingQ2 forecast favourable
5Weather-related delay provision — winter worksRisk£75,000£0S. OkaforOpen
6Subcontractor insolvency riskRisk£65,000£0L. PembertonMonitoring
7Labour rate reduction opportunity — Q3Opportunity-£55,0005,000 L. PembertonLikely
8Material buyback opportunity — surplus aggregateOpportunity-£40,000£0L. PembertonOpen
Totals£820,000 (R) / -£95,000 (O)Net £725,000